MONGLA AND DHALESWARI BRIDGES (BANGLADESH)

01/05/2014

Narrative description of Project:

Dhaleswari Bridge:

 – Total length L=406.85m.

 – Main Bridge: FCM, layout 60.2+2@89+60.2 = 298.4m.

 – Approach Bridge: Pre-cast “I” girder, layout: [45.07+[Main bridge]+45.07] 

Dhaleswari -2 Bridge:

 – Total length L=1380.98m.

 – Main Bridge: FCM, layout 59.9+2@89+59.9 = 297.8m.

 – Approach Bridge: Pre-cast “I” girder, layout: [12@44.0m+[Main bridge]+12@44.0m]

The Client/Main Consultant: SMEC Vietnam

Address: Level 15, 319 Building 63 Le Van Luong Street

Trung Hoa Ward, Cau Giay District, Hanoi

Consultant under the contract (in USD): USD 47,0000

Implementation Period:

  • Start date (month/year): 5/2014
  • Completion date (month/year): 6/2014

No. of senior professional staff: 04 engineers