Ha Noi Ring Road No.3 Project

29/09/2015

Project Description:

Ha Noi Ring Road No.3 – phase II, which was completed and opened to traffic in March 2013, has total length of 8,912Km, including 385m of road and 8,527km of viaduct, located in the median of Hanoi Ring Road No.3 – Phase I. There are 4 traffic lanes and 2 emergency parking lanes. The project’s design is appropriate to expressway standards with the speed of 100km/h. The total investment is more than VND 5.5 billion.

Client: THANG LONG PROJECT MANAGEMENT UNIT

Address: Hamlet 2, Linh Nam Street, Hoang Mai District, Ha Noi City, Viet Nam
Value of consultant services under the contract: USD 115,077

Implementation Period:
• Start date (month/year):7/ 2010
• Completion date (month/year): 3/2013
No. of senior engineers: 04
• Structure Engineer/ Assistant Engineer: 01
• Supervision Engineer: 03
Description of services provided by VEC Consultant:
Supplying Supervision Consultant Engineer.

   