LO RIVER BRIDGE (NOI BAI – LAO CAI EXPRESSWAY PROJECT)

06/07/2013

Narrative description of Project:

Noi Bai – Lao Expressway is designed in accordance with TCVN 5729-97. Total length of 264km. The minimum design speed of the first section is 100km/h.\

The Package A2 has total length of 22.12km.It includes 19 bridges (one large-scale bridge – Lo River Brige) 27 underpass culverts and 75 drainage box culverts.

Lo River Bridge: Balanced cantilever continuous girder bridge 3@40+78.5+3@110+78.5+5@40=807m. Bridge width: B=16,25m.

 

The Client: Vietnam Expressway Corporation (VEC), Ministry of Transport, Viet Nam

Address: Floor 4, 5, 6, Mitec building, Cau Giay District, Hanoi.

Consultant under the contract (in USD):

 USD 535,000  (for entire shop drawing of Package A2s)

Implementation Period:

  • Start date (month/year): 2009
  • Completion date (month/year): 2013

No. of senior professional staff: 09 engineers

Description of actual services provided by your staff within the assignment:

Topographic, Geologic surveys; Structure calculation and making working drawing for Lo River Bridge