LO RIVER BRIDGE (NOI BAI – LAO CAI EXPRESSWAY PROJECT)
06/07/2013Narrative description of Project:
Noi Bai – Lao Expressway is designed in accordance with TCVN 5729-97. Total length of 264km. The minimum design speed of the first section is 100km/h.\
The Package A2 has total length of 22.12km.It includes 19 bridges (one large-scale bridge – Lo River Brige) 27 underpass culverts and 75 drainage box culverts.
Lo River Bridge: Balanced cantilever continuous girder bridge 3@40+78.5+3@110+78.5+5@40=807m. Bridge width: B=16,25m.
The Client: Vietnam Expressway Corporation (VEC), Ministry of Transport, Viet Nam
Address: Floor 4, 5, 6, Mitec building, Cau Giay District, Hanoi.
Consultant under the contract (in USD):
USD 535,000 (for entire shop drawing of Package A2s)
Implementation Period:
- Start date (month/year): 2009
- Completion date (month/year): 2013
No. of senior professional staff: 09 engineers
Description of actual services provided by your staff within the assignment:
Topographic, Geologic surveys; Structure calculation and making working drawing for Lo River Bridge