HONG RIVER BRIDGE (NOI BAI – LAO CAI EXPRESSWAY PROJECT)
08/08/2013Narrative description of Project:
Noi Bai – Lao Expressway is designed in accordance with TCVN 5729-97. Total length of 264km.
The minimum design speed of the first section is 100km/h.The package A3 is 31.64km in length, designed of 4 lanes. It includes 17 bridges (one large-scale bridge- Hong River Bridge), 1 service station, 48 underpasses and 7 box culverts.
Hong River Bridge: Balanced cantilever continuous girder bridge 2@40+85+4@110+85+4@40=850m. Bridge width: B=16,25m
The Client: Vietnam Expressway Corporation (VEC), Ministry of Transport, Viet Nam
Address: Floor 4, 5, 6, Mitec building, Cau Giay District, Hanoi.
Consultant under the contract (in USD):
USD 619,465 (for entire shop drawing of Package A3)
Implementation Period:
- Start date (month/year): 2010
- Completion date (month/year): 2013
No. of senior professional staff: 09 engineers
Description of actual services provided by your staff within the assignment:
Topographic, Geologic surveys; Structure calculation and making working drawing for Hong River Bridge.